Corporate Finance Manual

CFM63300 · Foreign exchange: matching: anti-avoidance: FA2010: risk transfer schemes

  • CFM63310 · FA2010: risk transfer schemes: introduction
  • CFM63320 · FA2010: risk transfer schemes: example
  • CFM63330 · FA2010: risk transfer schemes: summary of the legislation
  • CFM63340 · FA2010: risk transfer schemes: meaning of ‘risk transfer scheme’: condition 1
  • CFM63350 · FA2010: risk transfer schemes: meaning of ‘risk transfer scheme’: conditions 2 and 3
  • CFM63360 · FA2010: risk transfer schemes: scheme losses and scheme profits
  • CFM63370 · FA2010: risk transfer schemes: calculating the ring-fenced losses
  • CFM63380 · FA2010: risk transfer schemes: calculating the relevant scheme profits
  • CFM63390 · FA2010: risk transfer schemes: the losses pool
  • CFM63400 · FA2010: risk transfer schemes: the profits pool
  • CFM63410 · FA2010: risk transfer schemes: utilising ring-fenced losses: same period
  • CFM63420 · FA2010: risk transfer schemes: utilising ring-fenced losses: subsequent periods
  • CFM63430 · FA2010: risk transfer schemes: ‘economic’ profits and losses
  • CFM63440 · FA2010: risk transfer schemes: the group
  1. Foreign exchange: matching: anti-avoidance: FA2010: risk transfer schemes: Contents
  2. FA2010: risk transfer schemes: calculating the ring-fenced losses

CFM63370 | FA2010: risk transfer schemes: calculating the ring-fenced losses

From HM Revenue & Customs · Corporate Finance Manual

Ring-fenced Scheme Losses

Where a company has made scheme losses (CFM63360) as part of a risk transfer scheme, a proportion of those losses will be ring-fenced. The reason why only a proportion of the ‘scheme loss’ is ring-fenced is to ensure that the relevant group obtains tax relief for the element of the loss that relates to a real economic loss to the group, when viewed as a whole. This would generally be that part of the loss that represents the ‘overhedge’ - i.e. the excess over which a normal hedge would have been obtained.

The rules for calculating the amount of loss to ring-fence are at CTA10/S937F and are calculated using the following formula:

(A - B - C ) / A

A = The total of the scheme losses made in the period in relation to the scheme by the members of the relevant group

B = The total of the scheme profits made in the period in relation to the scheme by the members of the relevant group

C= The pre-tax economic loss from the scheme

Pre-tax economic loss

The ‘pre-tax economic loss’ is the overall economic loss that the group makes, as a whole, by virtue of being party to the scheme, and prior to any tax implications.

Example

Using the example at CFM63320, and assuming that sterling has depreciated by 10% against yen, we can see how this works:

A = The loss on the yen borrowing (see CFM63360) = £13.9m

B = £0 (there are no profits made on any loan relationship or derivative contract)

C = The overall pre-tax loss made from the scheme - i.e. the loss on the yen borrowing of £13.9m less the profit made on the shareholding of £10m = £3.9m

So, the relevant proportion of the ‘scheme loss’ that is a ‘ring-fenced scheme loss’ is (£13.9m - £0 - £3.9m) / £13.9m = 71.2%.

As the ‘scheme loss’ was £13.9m, the ‘ring-fenced scheme loss’ is 72% of £13.9m = £10m