Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
VAT Construction

VCONST10000 · Zero-rating major interest grants in substantially reconstructed ‘protected buildings’

  • VCONST10010 · About this section
  • VCONST10100 · Basic conditions for zero-rating major interest grants in substantially reconstructed protected buildings
  • VCONST10200 · Imported definitions and constraints
  • VCONST10300 · What ‘substantially reconstructed’ means
  • VCONST10400 · Premiums and other payments
  • VCONST10500 · Holiday homes
  • VCONST10600 · ‘person substantially reconstructing a building’
  • VCONST10700 · First major interest grant in, or in any part of, the building, dwelling or its site
  • VCONST10800 · - Zero-rating major interest grants in substantially reconstructed ‘protected buildings’: apportionment
  1. Zero-rating major interest grants in substantially reconstructed ‘protected buildings’: contents
  2. Zero-rating major interest grants in substantially reconstructed ‘protected buildings’: first major interest grant in, or in any part of, the building, dwelling or its site

VCONST10700 | Zero-rating major interest grants in substantially reconstructed ‘protected buildings’: first major interest grant in, or in any part of, the building, dwelling or its site

From HM Revenue & Customs · VAT Construction

For a building to be ‘substantially reconstructed’, the reconstruction must, at least, meet one of the two conditions in Note 4 to Group 6 when the reconstruction is complete (VCONST10320).

This means that the only person that can have ‘person substantially reconstructing’ status and can make a zero-rated supply is the person that is in the position to make a major interest grant in a substantially reconstructed protected building.

Developers that grant a major interest in the building before it has been substantially reconstructed can’t zero-rate the supply.

A purchasing developer that takes over the project, completes the substantial reconstruction and grants a major interest in the building can zero-rate the supply to the extent that it is a ‘protected building’.