Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
Compliance Handbook

CH411000 · Charging penalties: contract settlement

  • CH411050 · Cases that can be settled by contract
  • CH411100 · Cases that need to be settled by contract
  • CH411125 · Offers including a suspended penalty
  • CH411130 · The contract settlement form (CSF)
  • CH411150 · Manager’s approval
  • CH411200 · Agreement with the taxpayer
  • CH411250 · Letter of offer received
  • CH411350 · Accepting the offer
  • CH411400 · Action at the end of suspension period
  • CH411450 · Employer Compliance Laptop Settlement System (ECLSS)
  • CH411500 · Recording penalties for MIS purposes
  1. Charging penalties: contract settlement: contents
  2. Charging penalties: contract settlement: accepting the offer

CH411350 | Charging penalties: contract settlement: accepting the offer

From HM Revenue & Customs · Compliance Handbook

The taxpayer’s offer must be authorised in accordance with the guidance at EM6402a.

Where the offer is payable in full you must, for Class 1, 1A and 6 contracts

  • complete the SAFE stencil in SEES - Forms and Letters. Send the completed SAFE stencil to either your SAFE nominee or the Centralised SAFE Team in Local Compliance to ask them to create a charge on SAFE, see EM6403. You should only use the SAFE 2 amendment stencil for amendments that you cannot process electronically

  • send the person the letter of acceptance as set out as in EM6410

  • update NPPS

When the Contract Settlement Form (CSF) is going to be stored electronically, the letter of acceptance should be saved and finalised in Caseflow/CRMM Case Document Store and must be named ‘Letter of acceptance’. The document classification should be ‘Offer and Certificate’.

Where a penalty is suspended you must

  • treat the amount of the suspended penalty as a separate instalment, see EM6306. Do not raise a SAFE charge for this instalment

  • where there are other instalments, make sure the suspended penalty instalment is the last instalment but again, do not take any action to raise a SAFE charge for the additional ‘suspended penalty’ instalment

Note: In cases where any penalties included in the offer are suspended, the ‘Net Offer’ amount on the SAFE Class 1 contract settlement stencil is not the same as the ‘Net Offer’ amount on the CSF. The latter has to be reduced by the amount of the suspended penalties included in the contract.

  • send the appropriate version of the letter of acceptance included at EM6410, see below:

  • for single payment offers with an additional ‘suspended penalty’ instalment, use the single payment acceptance letter

  • for instalment offers with an additional ‘suspended penalty’ instalment use the instalment payment acceptance letter

  • date the letter of acceptance on the day the suspension period starts

  • make sure suspension details are entered into NPPS

  • do not send the PDF copy of the NPPS3

The letter of acceptance should be saved and finalised in Caseflow/CRMM Case Document Store and must be named ‘Letter of acceptance’. The document classification should be ‘Offer and Certificate’.