FA04/S74 (2)(f) defines as within the scope of the Construction Industry Scheme
'operations which form an integral part of, or are preparatory to, or are for rendering complete, such operations as are previously described in this subsection, including site clearance, earth-moving, excavation, tunnelling and boring, laying of foundations, erection of scaffolding, site restoration, landscaping and the provision of roadways and other access works'.
This provision aims to cover those activities that are characteristic features of construction, but which are not dealt with specifically in other parts of FA04/S74.
Preparatory operations
This provision covers preparatory operations that enable construction work proper to proceed such as
site preparation
site decontamination
site clearance (including demolition and tree-felling)
Direct collection of road planings (see below)
earthmoving on site
marking out
excavation
tunnelling
boring (except for surveying purposes)
laying foundations
erecting scaffolding, falsework and formwork
installation of traffic management equipment
asbestos removal.
However, the following activities are not considered to be construction operations
delivery of materials, including liquid concrete
transport of spoil from site
tree-felling and tree surgery in the course of forestry or estate management.
Removal of road planing from site
Where haulage vehicles are used to collect road planing directly from the planer in one single process, HMRC consider such work to be an integral part of the preparatory construction operations, therefore these works will be within the scope of CIS. The removal and transportation of planing/spoil from site, which do not form part of any preparatory operations, is not considered to be within the scope of CIS.
Integral operations
This provision covers operations that are an integral part of construction
transport of materials on site
construction of site facilities
traffic management services
plant hire with operator for use on site.
disinfecting of reservoirs/water treatment facilities, either during or on completion of their construction
cleaning of road surfaces when done as part of the actual construction of the road, for example where the surface needs to be cleaned or damped down prior to the application of a further layer.
Finishing operations
This provision covers operations that bring a construction project to completion such as
site restoration and landscaping, including pumping out and draining of water
installation of instrumentation systems such as building environmental controls
installation, structural repair and painting of lamp standards, permanent traffic lights, parking meters, traffic signs and other street furniture
dismantling scaffolding, falsework and formwork
screeding, and the fitting of flooring and floor-coverings (including vinyl and linoleum but not carpeting) where these form part of the building specification
installation of building fittings such as safety eye-bolts
kitchen and bathroom fitting
tiling
fitting of thermal insulation, lagging or soundproofing as part of a wider project of construction
shop fitting
installation of built-in refrigeration equipment, such as cold stores (not free-standing refrigerators)
installation of fixed furniture (except seating) for example, shelving and fixed work stations.
However, the following activities are not considered to be construction operations
manufacture and delivery of building materials
non-structural repair of street furniture (for example, replacement of lighting elements or defective components in traffic lights or parking meters)
installation of seating
fitting of carpeting (this is excluded in all circumstances)
fitting of vinyl and other floor-coverings in premises not undergoing construction or alteration
fitting of thermal insulation or soundproofing in premises not undergoing construction where this has no effect on the fabric of the building.