Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
Construction Industry Scheme Reform Manual

CISR15000 · The Scheme: payments

  • CISR15010 · Introduction
  • CISR15020 · Definition
  • CISR15030 · 'contras' and 'set-offs'
  • CISR15040 · Retention payments
  • CISR15050 · Nominees and debt factors
  • CISR15060 · Materials
  • CISR15070 · Land purchases
  • CISR15080 · The Scheme: contract payments: travel, subsistence and accommodation
  • CISR15090 · Plant hire as 'materials'
  • CISR15100 · VAT
  • CISR15110 · CITB levy
  • CISR15120 · Contractor deductions (for example, administration, PLI)
  • CISR15130 · Contractors paying for work done on subcontractor's land
  • CISR15140 · Expenditure by certain businesses on their own property - 'own-build'
  • CISR15150 · Small payments
  • CISR15160 · Small payments arrangement - examination of applications
  • CISR15170 · Managing agents
  • CISR15180 · Payments under a private finance initiative (PFI) arrangement
  • CISR15600 · Contents (A)
  1. The Scheme: payments: contents
  2. The Scheme: payments: 'contras' and 'set-offs'

CISR15030 | The Scheme: payments: 'contras' and 'set-offs'

From HM Revenue & Customs · Construction Industry Scheme Reform Manual

You may encounter the following terms in certain situations where a contractor withholds part of a contract payment.

‘Contra’

A ‘contra’ is a charge for goods or services supplied to the subcontractor. For example, on a contract worth £200, the contractor gives the subcontractor some surplus materials and restricts payment by £50.

A ‘contra’ does not reduce the ‘payment’ from which the deduction may have to be made. It is in effect a ‘payment’ by the contractor to the subcontractor. In the example given, and assuming that the materials are not used in carrying out the construction operations, the deduction should be calculated on the full contract value of £200.

‘Set-Off’

A ‘set-off’ arises when a contractor does not make a payment because the contractor believes there has been a breach of contract. For example, £400 of a £2,000 contract is withheld because the work is below standard.

The ‘set-off’ reduces the ‘payment’ from which a deduction may have to be made. It is not a payment by the contractor to the subcontractor. In the example shown, the deduction should be made from £1,600.