Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
Construction Industry Scheme Reform Manual

CISR15000 · The Scheme: payments

  • CISR15010 · Introduction
  • CISR15020 · Definition
  • CISR15030 · 'contras' and 'set-offs'
  • CISR15040 · Retention payments
  • CISR15050 · Nominees and debt factors
  • CISR15060 · Materials
  • CISR15070 · Land purchases
  • CISR15080 · The Scheme: contract payments: travel, subsistence and accommodation
  • CISR15090 · Plant hire as 'materials'
  • CISR15100 · VAT
  • CISR15110 · CITB levy
  • CISR15120 · Contractor deductions (for example, administration, PLI)
  • CISR15130 · Contractors paying for work done on subcontractor's land
  • CISR15140 · Expenditure by certain businesses on their own property - 'own-build'
  • CISR15150 · Small payments
  • CISR15160 · Small payments arrangement - examination of applications
  • CISR15170 · Managing agents
  • CISR15180 · Payments under a private finance initiative (PFI) arrangement
  • CISR15600 · Contents (A)
  1. The Scheme: payments: contents
  2. The Scheme: payments: contractors paying for work done on subcontractor's land

CISR15130 | The Scheme: payments: contractors paying for work done on subcontractor's land

From HM Revenue & Customs · Construction Industry Scheme Reform Manual

Under SI2005/2045 reg 19, mainstream contractors may request authorisation not to apply the Scheme to small contracts or payments for construction operations amounting to less than £1,000 (excluding the cost of materials):

  • where the contractor is paying a subcontractor to undertake work that falls within the Scheme on the subcontractor’s own property, or

  • where the contractor is paying a subcontractor to undertake work on any agricultural property of which the subcontractor is a tenant.

An example of this type of payment is where a Utility Company lays a pipeline across some land and pays the land owner or tenant to fill in the hole after the pipeline has been laid.

To request authorisation not to apply the Scheme to such payments, contractors should contact the CIS Helpline and give us the following information:

  • details of the construction work to be done

  • who will be doing the work

  • where the work will be done

  • the cost of the work.

Where the request for authorisation not to apply the Scheme to payments of this nature satisfies the requirements set out above, you may grant such authorisation.