Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
Corporate Intangibles Research and Development Manual

CIRD63230 · Land Remediation Relief: Subcontractors

  • CIRD63235 · Land Remediation Relief: Subcontractors: Payments to an unconnected sub-contractor - on or after 1 April 2009
  • CIRD63240 · Land Remediation Relief: Subcontractors: Payment to a connected sub-contractor - on or after 1 April 2009
  • CIRD63245 · Payments to a connected sub-contractor - relevant expenditure of the sub-contractor
  • CIRD63250 · Payments to an unconnected sub-contractor - on or before 31 March 2009
  • CIRD63255 · Payments to a connected sub-contractor: on or before 31 March 2009
  • CIRD63260 · Payments to a connected sub-contractor - relevant expenditure of the sub-contractor
  • CIRD63265 · Land Remediation Relief: Verification
  • CIRD63270 · Land Remediation Relief: Preliminaries
  1. Land Remediation Relief: Subcontractors: Contents
  2. Land Remediation Relief: Preliminaries

CIRD63270 | Land Remediation Relief: Preliminaries

From HM Revenue & Customs · Corporate Intangibles Research and Development Manual

FA01/Sch22/Para2 (5)

CTA09/S1144

Companies involved in developing land will incur expenditure described as “preliminaries” or “global costs”. These are costs that are not particular to a particular part of the project. The types of expenditure which may be included under this heading include site services, security, temporary works, or safety measures.

Preliminaries will be incurred whether or not the site is contaminated. A simple apportionment of preliminaries is therefore not appropriate as these costs would have arisen whether or not the site was affected by contamination.

Land Remediation Relief will only be available if the amount of expenditure on preliminaries is increased specifically because the land is in a contaminated state. In this situation only the additional cost qualifies for Land Remediation Relief.