COM71000 · Enquiries: CTSA enquiries

  • COM71001 · Introduction
  • COM71005 · Time limit for opening an enquiry
  • COM71010 · Opening an enquiry
  • COM71011 · Functions
  • COM71013 · Opening an enquiry (Action Guide)
  • COM71020 · Taxpayer amendments
  • COM71021 · Forms
  • COM71030 · Repayment during enquiry
  • COM71040 · Making jeopardy amendments
  • COM71041 · Making jeopardy amendments (Action Guide)
  • COM71050 · Appeals against jeopardy amendments
  • COM71051 · Appeals against jeopardy amendments (Action Guide)
  • COM71060 · Enquiry into return for the wrong period
  • COM71061 · Enquiry into return for the wrong period (Action Guide)
  • COM71080 · Transferring an enquiry to FIS
  • COM71090 · Closing an enquiry: non-contract settlements
  • COM71091 · Closing an enquiry: non-contract settlements (Action Guide menu)
  • COM71092 · Closing an enquiry: non-contract settlement cases (Action Guide)
  • COM71093 · Closing an enquiry: manual closure notices (Action Guide)
  • COM71094 · Closing an enquiry non-contract settlement helpcard for caseworkers
  • COM71095 · Closing an enquiry non-contract settlement helpcard for COTAX operators
  • COM71100 · Closing an enquiry: reissuing a closure notice
  • COM71105 · Closing an enquiry: error in issuing a closure notice
  • COM71110 · Closing an enquiry: revenue amendments
  • COM71111 · Closing an enquiry: revenue amendments (Action Guide)
  • COM71120 · Closing an enquiry: closing an enquiry: contract settlements
  • COM71121 · Closing an enquiry: closing an enquiry: contract settlements (Action Guide)
  • COM71122 · Closing an enquiry: closing an enquiry: contract settlements helpcard for caseworkers
  • COM71123 · Closing an enquiry: closing an enquiry: contract settlements helpcard for COTAX operators
  • COM71125 · Partial closure notice
  • COM71126 · Partial closure notice (Action Guide)
  • COM71130 · Closing an enquiry: discovery assessments & determinations
  • COM71140 · Closing an enquiry: enquiries under Schedule 1A TMA 1970
  • COM71141 · Closing an enquiry: enquiries under Schedule 1A TMA 1970 (Action Guide)
  1. Enquiries: CTSA enquiries: contents
  2. Enquiries: CTSA enquiries: closing an enquiry: closing an enquiry: contract settlements helpcard for COTAX operators

COM71123 | Enquiries: CTSA enquiries: closing an enquiry: closing an enquiry: contract settlements helpcard for COTAX operators

From HM Revenue & Customs · COTAX Manual

If you are a COTAX operator and have been asked by a caseworker to close an enquiry in a contract settlement case, consider steps 1 - 14 below. The guide is presented as follows.

ActionSteps
General guidanceStep 1
Initial actionsSteps 2 - 5
To finalise the enquiry on the IT systemsSteps 6 - 8
Further actions requiredStep 9 - 14

General guidance

1. You must have the COTAX CT Co-ordinator role to carry out all the required actions. The caseworker will give you full instructions on the entries that are needed in the closure notice and the CT chargeable figure that will result. You must not use function RAMA (Record/Amend Assessment) to select option ‘prepare a closure notice with rev amdt’ where an enquiry is to be concluded by contract settlement. You will not be asked to disturb any assessments or late filing penalties on the Accounting Periods (APs) under enquiry.

If the instructions you receive from the caseworker ask you to issue a closure notice, any assessment or late filing penalties, you think the case is subject to a contract settlement and the instructions do not make it clear that the company or agent has insisted on the issue of a closure notice before the contract settlement is finalised, refer the case back for clarification.

Initial actions

2. Has the caseworker indicated that there is an overpayment on an Accounting Period (AP) outside the enquiry period?

If yes, go to step 8.

If no, go to step 3.

3. Has the caseworker indicated that there is an amount available to set off against the settlement charge?

If yes, go to step 9.

If no, go to step 4.

4. Has the caseworker indicated that there is an overpayment on COTAX that exceeds the amount needed to cover the contract settlement charge?

If yes, go to step 10.

If no, go to step 5.

5. Has the caseworker indicated that the company or agent insists on the issue of a closure notice before the contract settlement has been finalised?

If yes, go to step 11.

If no, go to step 6.

Top of page

To finalise the enquiry on the IT systems

6. The caseworker’s instructions will ask you to close the enquiry on COTAX. Use function MAPS (Maintain AP signals) to enter the date on which the enquiry was closed.

7. If the enquiry was recorded on Caseflow and you have access to the record, make the entries the caseworker has given you then go to step 8.

8. Has the caseworker indicated that there is an overpayment on an Accounting Period (AP) outside the enquiry period?

If yes, please complete the Intelligent Payment Processing (IPP) Single Form, if repayment interest is applicable, please ensure you leave a COTAX note advising of the appropriate Effective Date of Payment (EDP).

If no, go to step 9.

Top of page

Further actions required

9. Where there are amounts available to set off against the settlement charge, follow the caseworker’s instructions and use function REOD (Direct Reallocation out of COTAX) to transfer the overpayment on the COTAX record to OAS so it can be reallocated to the contract settlement charge and tell the caseworker the OAS number so they can complete the Intelligent Payment Processing (IPP) Single Form.

10. Where an overpayment on COTAX exceeds the amount needed to cover the contract settlement charge, the caseworker’s instructions will either ask you to:

  • reallocate the necessary amount using function REOD

  • reallocate the balance against other liabilities using function REWD (Direct Reallocation within COTAX)

  • repay the remaining balance (if any) using function DIRR (Direct Repayment)

Tell the caseworker the OAS number from the function REOD reallocation so they can complete the Intelligent Payment Processing (IPP) Single Form.

11. Where the company or agent insists on the issue of a closure notice before the contract settlement has been finalised, the instructions you receive from the caseworker will make it clear that a closure notice is to be issued even though it is a contract settlement case. Use function RAMA (Record/Amend Assessment) option ‘closure notice with rev amdt’.

12. Amend the figures indicated by the caseworker.

13. Check that the amount of CT chargeable agrees with the figure the caseworker has given you. If it does not agree, use the button to produce a printout of the screen and refer it to the caseworker for further guidance. Use the button to abandon function RAMA until you receive fresh instructions.

14. Issue the assessment.