Official guidance
Debt Management and Banking Manual

DMBM557500 · Debt and return pursuit: Child Benefit overpayments: recovery from continuing entitlement

  • DMBM557510 · General
  • DMBM557530 · Commencing direct recovery action
  • DMBM557540 · Long-term recovery review
  • DMBM557550 · Weekly paid cases recovery near an end
  • DMBM557560 · Recovery complete
  1. Debt and return pursuit: Child Benefit overpayments: recovery from continuing entitlement: contents
  2. Debt and return pursuit: Child Benefit overpayments: recovery from continuing entitlement: commencing direct recovery action

DMBM557530 | Debt and return pursuit: Child Benefit overpayments: recovery from continuing entitlement: commencing direct recovery action

From HM Revenue & Customs · Debt Management and Banking Manual

Some content of this manual is being considered for archiving. If there is content you use regularly, please email [email protected] to let us know as soon as possible.

Action on BF code 1 expiry

  • Calculate the recovery start date; for:

    • weekly paid cases, ignore the week you are working in, ignore the next three weeks and start recovery from the following week

    • four-weekly paid cases, ignore the current payment cycle and start recovery from the first week of the following payment cycle.

  • Issue SEES letter CBOP170A to confirm details of the recovery plan.

  • Set OPREC BF to delayed code 2 BF Code 5.

  • Set the BF date for a Mon or Tues (mirroring the Child Benefit payday); for:

    • weekly cases set the BF for the week prior to the recovery start date

    • four-weekly cases set the BF for the first week of the payment cycle in which recovery will commence.

  • Update the OPREC notepad with “CBOP170A issued withhold from (Date)(Initials)”.

Action on BF code 5 expiry or after customer contact

Customer contact only

  • Negotiate recovery following the guidance at DMBM557270.

  • Issue SEES letter CBOP170A unless the customer has confirmed they do not require one.

OPREC action to show recovery

  • Highlight ‘recovery’ and select ‘edit’.

  • Select ‘immediate’.

  • Select ‘benefit deductions’.

  • Click on ‘benefit deductions’ tab at the top of the page.

  • Select ‘add’.

  • Enter 28 in deductions from.

  • Enter 1 in benefit payday.

  • Enter the weekly amount of recovery.

  • Enter recovery start date (always use Monday date).

  • Select ‘OK’.

  • A prompt box may appear advising that you are starting a recovery over £15, please ignore and select ‘OK’.

  • Make a note of the recovery end date.

OPREC action to set BF

  • Click on the ‘recovery’ tab at the top of the page.

  • If recovery will take over one year, leave BF code as 12 and set BF period for 52 weeks.

  • If recovery will be complete within one year, change to BF code 9 and set the ‘BF date’ to Mon or Tues mirroring the Child Benefit payday; for:

    • weekly cases, set the BF date for the week prior to the recovery end date

    • four-weekly cases, set the BF date for the week of the final deduction.

  • Select ‘OK’.

  • If any fulltime exclusion dates occur within the recovery period, add ££ in front of the first name on OPREC.

CBOL action

Open the ‘corres’ indicator on CBOL by using dialogue 3 and transaction number 2.

CBUS action to start recovery on the Child Benefit Computer System (CBCS)

  • Select ‘C’ screen – ‘instrument of payment code’; for:

    • weekly cases, enter 56

    • four-weekly cases, enter 44.

  • Enter weekly amount of recovery (consider uprating).

  • Enter start date.

  • Enter ‘C’ in pay code.

  • Click on ‘Lost & Ret/Rec’ tab at the top of the screen.

  • Select ‘yes’ from the ‘long term recovery’ dropdown menu.

  • Select ‘E’ screen (consider uprating).

  • Click on ‘questions’ tab at the top of the page.

  • Select ‘yes’ from the ‘is the case to be cleared’ dropdown menu.

  • For ‘misc BF date’ enter a date one month after the end of recovery.

  • Select ‘update’.

PreviousNext