Skip to content
Solved
SearchBrowse
Sign in

Contents

Official guidance
VAT Assessments and Error Correction

VAEC6000 · General assessment procedures

  • VAEC6010 · Pre-assessment letter
  • VAEC6020 · When to issue a pre-assessment letter
  • VAEC6030 · Specimen pre-assessment letter
  • VAEC6040 · What to do when pre-assessment letter issued
  • VAEC6050 · The computer system
  • VAEC6060 · Objectives and risks on the system
  • VAEC6070 · Definition of an assessment
  • VAEC6080 · Time limit implications in making and notifying assessments
  • VAEC6090 · De minimis levels
  • VAEC6100 · Who makes an assessment
  • VAEC6110 · Importance of avoiding delay
  • VAEC6111 · Interaction with inaccuracy penalties and importance of avoiding delay
  • VAEC6120 · Accuracy checks
  • VAEC6130 · Disclosure of calculations
  • VAEC6140 · Accounting period has not yet ended
  • VAEC6150 · Global or bulk assessments
  • VAEC6160 · Difficulty in attributing VAT to accounting periods
  • VAEC6170 · Assessments to partnerships
  • VAEC6180 · Assessments to VAT groups registrations
  • VAEC6181 · Change in representative member
  • VAEC6190 · Assessments to missing traders
  • VAEC6200 · Supplementary assessments
  • VAEC6210 · When to use supplementary assessments
  • VAEC6220 · Payment of assessments
  1. General assessment procedures: contents
  2. General assessment procedures: Specimen pre-assessment letter

VAEC6030 | General assessment procedures: Specimen pre-assessment letter

From HM Revenue & Customs · VAT Assessments and Error Correction

The procedural guidance in this manual only covers the VAT Mainframe and VISION processes. For guidance on the Making Tax Digital and ETMP processes for fully migrated customers, see VAEC0200 and the Making Tax Digital for VAT compliance toolkit.

A pre-assessment specimen letter, VAT(LC)15: Pre-assessment letter, is available on SEES.

Remember it is crucial that

  • any legal references on the letter are correct and that there is no suggestion that the assessment has already been made

  • your letter informs the business of your intended decision and that it is accompanied by a schedule which clearly demonstrates to the business the basis of your calculations,

  • your letter refers to the potential liability to interest and, if appropriate, a penalty, and

  • gives the business a deadline, normally twenty one days, to respond.